Marlin Street Reconstruction

Description: The proposed improvements to Marlin Street include a new storm drain system, new heavy-duty asphalt pavement and sub grade and a new lighting system along the street which will provide visibility during any operations in the area and for security.
 
Designer: Construction Engineering Group (CEG)
Contractor/CM:  Rush Construction Inc.
Project Costs: $1,933,412.00
Completion     Date: February 2017 (Final Completion)
Status:  Asphalt and concrete pavement has been placed on Marlin St. and on the pond in Auto Port’s lot. The lift station is already installed but testing, training and connections are still pending. The Contractor is working with the Punch list items and the removal of temporary facilities.  Also, Rush is working on the remaining contingency and allowance requests in order to close out the project.  

Parrish Medical Center Building



Description: 
This project is the construction of the a new +/- 9,600 square foot facility to house Parrish Medical Center.
 
Designer: Construction Engineering Group (CEG)
Contractor/CM:  Rush Construction Inc.
Project Costs: $1,700,000.00
Completion     Date: June 2017
Status:  Exterior concrete block wall has been placed. Concrete slab and underground plumbing has been installed. Contractor will being roof steel installation this week.