Building Department 

Click here to view the Building Department Page, where you can find more information about performing alterations, repairs, maintenance, and new construction to tenant properties.

Featured Projects

North Cargo Berth 8:

DJI_0004.JPG


Description: This project consists of three phases; bulkhead construction, pier extension, and upland paving. 
Designer:  Atkins/Jacobs
Contractor:  Orion Marine
Project Costs: $17,924,803.87
Completion Date: Summer 2019
Status:  Orion Marine has completed both concrete pile and steel pipe/sheet pile installation. Contractor is currently working on connecting the new bulkhead steel combination wall to the upland anchor wall with the installation of the tie back anchor rods. Contractor is forming and pouring the new concrete bulkhead wall. Project dredging activities are schedule to begin mid-December.
 
NCB8 pier extension and upland improvements design continues with design at 30%.

Northside Roadway Network:


Description: This project consists of improvements to the North side cruise terminals roadways to relieve traffic  congestion, augment pedestrian safety and expand and improve the capacity of existing roads
Design/Builder:  Ivey’s Construction
Project Costs: $6,248,323.00
Completion Date: Summer 2019
Status:  The project was approved by the CPA Board of Commissioners on October 31, 2018 and the Notice to Proceed was issued. The contractor is working with the procurement of materials. Construction works are expected to start by the end of November.  
 

Port Wide Wayfinding and Signage Project:

Description: This project is the design, permitting, fabrication and installation of vehicular directional signs and gateway signs to be located throughout Port Canaveral, on SR 528 and A1A.
Designer: BEA
Contractor:                Ivey’s Construction Co.  
Project Costs: $7,981,978.28
Completion Date: Spring 2019
Status:  NTP has been issued to Ivey’s Construction for the completion of the design package. CPA has received the 90% design package for the FDOT signs and is currently under review. Design team is working on submission of internal signage package. Design anticipated to be complete late May.

Contact Information

 
Bill Crowe, P.E.
Vice President, Engineering, Construction and Facilities
Tel: 321-783-7831 ext. 208
bcrowe@portcanaveral.com
William J. Hammond Bob Musser Jr.
Chief Building Official Director - Port Environmental
Tel: 321-783-7831 ext. 299 Tel: 321-783-7831 ext.256
whammond@portcanaveral.com bmusser@portcanaveral.com